Construction Document Templates and Forms sold here - Credit cards accepted Templates sold
Site Map x Follow us on Twitter! x RSS Feed Email us!
Blank
Word, Excel, PDF and Powerpoint templates complete with formulas and layouts. x Find the Largest range of construction document templates or forms here!
x x
Download now!
Home Page Free Templates Package Deals News & Articles Frequently Asked Questions

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Clause 14 Programme Guideline

Contractors are compelled by the FIDIC Contract to submit a Clause 14 programme within 28 calendar days after receipt of the Letter of Acceptance.

This programme should cover all aspects of the design, approval, procurement, construction, installation, removal and commissioning of the temporary and permanent works. The programme should generally be prepared in a bar chart format that will indicate the critical path for the Project (Red).

Programme Content:
The programme shall indicate, but not be limited to:-

• Award of Contract• Building Permit Approval• Demarcation complete • Contractual Milestone Dates • Completion Date • Opening Date• Shop drawing production trade by trade • Shop drawing approval periods • Procurement windows for key materials, plant and equipment • Temporary Works installation and removal (including cranes)• Subcontract tender periods and award dates • Subcontract design and installation periods • Approval of As Built drawings • Structure Weather tight • Mains Power 'on' date • Mains water 'on' date •Mains drainage 'connection' date (Stormwater and Foul water) • Chilled water 'on' date • AC in Building 'on' date • Finishes complete• Client Access dates • Plant equipment commissioning periods • Staff training periods • Temporary power supply 'off' date • Temporary water supply 'off' date • Approval of O&M Manuals • Final Clean

Critical Path Analysis
In order to understand the critical path of a Project, you must include a critical path analysis in the tender programme and the Clause 14 programmes. This is critical in terms of understanding the impact when delays occur.

Manpower Resource
Also input the manpower resources and production rates into the programme to substantiate the resulting bar chart. In doing so you will be able to provide a separate resource histogram indicating the supervision and manpower allocation over the Contract duration. It is generally a good idea that a copy of this histogram is included with the Tender submission.

Plant and Equipment
As above you should also input the plant and equipment resources and production rates into the programme to substantiate the resulting bar chart. And provide a separate resource histogram indicating the plant and equipment allocation over the Contract duration.

Testing and Comissioning Programme
Most Contracts requires the submission of a detailed system testing and commissioning programmes prior to the commencement of the testing and commissioning of the MEP plant and equipment. These programmes should be supported by an overall commissioning strategy supplemented by detailed system commissioning method statements. This commissioning regime must be based on a "cause and effect" strategy.

 

 

 

 

Other Articles

point

Taking Over or Completion Certificates

 

point

Hudson Formula and Extension of Time Claims

point

PC Sums and Provisional Sums Clarified

 

point

Tracking delay events

point

Labour Costing

 

point

Pricing Preliminaries

point

Pricing Concrete Formwork and Reinforcing

 

point

Dayworks in the Construction Industry

point

Prolongation Cost Claims - An eye for detail

 

point

Demonstrating a Loss of Productivity Claim

point

Causes of Lost Productivity Claims

 

point

Importance of Good Record Keeping

point

Supervision of the Works

 

point

Programme for the Works

point

Clause 14 Programme

 

point

Monthly Progress Reports

point

Method Statement Guideline

 

point

Project Specific Health and Safety Plan

point

Format of O and M Manuals

 

point

Application for Final Certificate

point

Variations or Extra Work

 

point

Business Letter writing fundamentals

 

 

 

  TEMPLATES MENU
Project Management Templates Commercial Cost Control
Project Management Templates Project Management
Contractual Templates Contractual
Tendering Templates Tendering / Estimating
Health & Safety Templates Health & Safety
Human Resources Templates Human Resources
Quality Control Templates Quality Control
Quality Control TemplatesSafety Training
PDF Templates PDF Templates
PDF Templates Procedure Manuals
Full house special FULL HOUSE Special
Smartphone Apps Smartphone Apps
Client List Client List
 
 
 
Online Construction Document Templates developed by Contractors for Contractors
Site Lock Valid HTML 4.01 Transitional Privacy Eco Certified Construction Document Templates
Copyright © Online-TemplateStore 2009-2017
spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer