Construction Document Templates and Forms sold here - Credit cards accepted Templates sold
Pinterest connect x Follow us on Twitter! x RSS Feed Email us!
Blank
Word, Excel, PDF and Powerpoint templates complete with formulas and layouts. x Find the Largest range of construction document templates or forms here!
x x
Download now!
Home Page Free Templates Package Deals News & Articles Frequently Asked Questions

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Tracking Delay Events

The procedure of submitting notices for construction delay events are normally well defined in a Contract. The FIDIC Contract for example prescribes that a delay event must be notified formally within 28days of the Contractor becoming aware of that event or its impact. In addition the Contractor is required to submit further particulars or updates every 28days until the final impact is determined and or a claim is submitted. The reality is that this process and its procedures generally becomes an administrative nightmare for many Contractors. Let's firstly look at the requirements of a valid notice and then secondly identify what tools can be used to track these events and maintain the 28day requirement.

A valid notice should be in writing and on a company letterhead addressed to the Engineer with a copy to the Employer. The letter must clearly state that it is a Notice of Delay / Potential delay and it should also identify under which clauses of the Contract the notice is being made. The notice must also describe the event and identify which milestone or contract date will be likely affected. Close the letter by identifying what required actions by the Engineer could minimize or negate the delay. A good template complying with all these requirements is available in the Contractual Management package (view template).

Once submitted the tracking of and keeping notices valid, that is submitted every 28days, become the next challenge.

When creating a tracking schedule, first enter all your events, letter references and dates into a spreadsheet. This will now give you a simple basis to track your notices and references.Secondly add a formula to the date column that will add say 26 days (2 days to write and send letter) to the last event date. This will then automatically calculate when the next notice should be prepared and submitted. Thirdly, maintain the schedule by adding each new letter reference, date in the follow-up cell and a formula to track your next notice due date. This spreadsheet should be submitted to the Engineer and Client on a monthly basis to identify which events are still "Open" and which are "Closed".

If you are having difficulties in creating such a tracking schedule why not try our professional preformatted Delay Event Schedule (view template).Our template allows you to enter your prescription period that 21, 28 days, etc. as this will determine the next due date. The template also provide a logical and clear space for letter referencing and lastly flags (colour) the current status of the notice via conditional formatting. That is it will red flag when the next notice submission has passed or amber if it is due in a few days. The schedule is easily understood and logically summarizes all events, notices made, re-submissions and the next notice due date. This compact report can also be submitted as part of the monthly progress report or your actual claim submission.

Face it, the last thing you want to happen is for your notified delay to be time barred or rejected. Get peace of mind by making sure your notices are valid and monitored using a custom designed claim tracking schedule. - Refer to the Construction Management Package.

 

 

 

 

Other Articles

Taking Over or Completion Certificates

 

Hudson Formula and Extension of Time Claims

PC Sums and Provisional Sums Clarified

 

Tracking delay events

Labour Costing

 

Pricing Preliminaries

Pricing Concrete Formwork and Reinforcing

 

Dayworks in the Construction Industry

Prolongation Cost Claims - An eye for detail

 

Demonstrating a Loss of Productivity Claim

Causes of Lost Productivity Claims

 

Importance of Good Record Keeping

Supervision of the Works

 

Programme for the Works

Clause 14 Programme

 

Monthly Progress Reports

Method Statement Guideline

 

Project Specific Health and Safety Plan

Format of O and M Manuals

 

Application for Final Certificate

Variations or Extra Work

 

Business Letter writing fundamentals

Change Management Schedule

 

Constructive Acceleration

Extension of time claims

 

Monthly Cost reporting concept

Penalties or Liquidated Damages

 

Claim Structure - how to prepare a claim?

 

 

 

  TEMPLATES MENU
Commercial Cost Control
Project Management
Contractual
Tendering / Estimating
Health & Safety
Human Resources
Quality Control
Safety Training
PDF Templates
Procedure Manuals
FULL HOUSE Special
Smartphone Apps
Client List
 
 
 
Online Construction Document Templates developed by Contractors for Contractors
Site Lock Valid HTML 4.01 Transitional Privacy Eco Certified Construction Document Templates
Copyright © Online-TemplateStore 2009-2021
spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer