Construction Document Templates and Forms sold here - Credit cards accepted Templates sold
Pinterest connect x Follow us on Twitter! x RSS Feed Email us!
Blank
Word, Excel, PDF and Powerpoint templates complete with formulas and layouts. Your one stop Construction Template Store Find the Largest range of construction document templates or forms here!
x x
Download now!
Home Page Free Templates Package Deals News & Articles Frequently Asked Questions

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Penalties or Liquidated damages in construction contracts

Provisions for Penalties, Liquidated Damages or delay damages (a monetary value representing the damage caused by the delay) are contained in most construction contracts.

Liquidated damages are not penalties, they are pre-determined damages set at the time that a contract is entered into, based on a calculation of the actual loss the client is likely to incur if the contractor fails to meet the completion date. They might include, rent on temporary accommodation, removal costs, extra running costs, finance costs and so on.

Penalty clauses on the other hand are specified sums of money that is applied in the event of a breach in contract and bears no reflection on the actual loss suffered by the Employer or Client.

Both of these deductions are imposed where the employer has specific deadlines or other requirements and will experience a loss of revenue, loss of use of the premises if the project is delivered late or have to pay additional supervision and administration costs relating to the late completion.

The contract document will specify the value of the LD’s, damages or penalties per day, per week or per month, or the extent of the penalties should specific requirements not be achieved.

LD’s or Penalties can be deducted from interim payment certificates as soon as they occur and can be objectively quantified. They are based on the difference between the time that the works were actually completed and the time according to the contract when they were supposed to be completed.

However, if the project is delayed by an event that impacts on the completion date, but is not the fault of the contractor, then this may constitute a 'compensation / claim event’ for which the contractor may be granted an extension of time (ie the completion date in the contract is adjusted), and the contractor may be able to make a claim for loss and expense. If such events exist and notices have been submitted by the contractor, then the client cannot deduct LD’s / penalties until such time that the impact of these events have been determined.

 

 

 

Other Articles

Business Letter writing fundamentals

 

Hudson Formula and Extension of Time Claims

PC Sums and Provisional Sums Clarified

 

Tracking delay events:

Labour Costing

 

Pricing Preliminaries

Pricing Concrete Formwork and Reinforcing

 

Dayworks in the Construction Industry

Prolongation Cost Claims - An eye for detail

 

Demonstrating a Loss of Productivity Claim

Causes of Lost Productivity Claims

 

Importance of Good Record Keeping

Supervision of the Works

 

Programme for the Works

Clause 14 Programme

 

Monthly Progress Reports

Method Statement Guideline

 

Project Specific Health and Safety Plan

Format of O and M Manuals

 

Application for Final Certificate

Variations or Extra Work

 

Business Letter writing fundamentals

Change Management Schedule

 

Constructive Acceleration

Extension of time claims

 

Monthly Cost reporting concept

Penalties or Liquidated Damages

 

Claim Structure - how to prepare a claim?

 

 

 

  TEMPLATES MENU
Commercial Cost Control
Project Management
Contractual
Tendering / Estimating
Health & Safety
Human Resources
Quality Control
Safety Training
PDF Templates
Procedure Manuals
FULL HOUSE Special
Smartphone Apps
Client List
 
 
 
Online Construction Document Templates developed by Contractors for Contractors
Site Lock Valid HTML 4.01 Transitional Privacy Eco Certified Construction Document Templates
Copyright © Online-TemplateStore 2009-2021
spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer spacer